Three Ukrainian nuclear power plants have not fully restored connections with power lines after shelling on August 26 - IAEA.
06.09.2024
826

Journalist
Shostal Oleksandr
06.09.2024
826

Rivne, South Ukrainian, and Chornobyl nuclear power plants have not yet restored connections with all external power lines due to shelling on August 26. This was reported by the International Atomic Energy Agency.
"IAEA teams from Rivne, South Ukrainian, and Chornobyl NPPs reported that these sites have not yet restored connections with all external power lines after the large-scale military actions on August 26 targeted substations important for nuclear safety. The teams also reported air raid alarms on most days last week," the IAEA statement said.
It is currently unknown how this affects the operation of the NPPs.
However, drone overflights were recorded near the Khmelnytsky NPP.
In addition, Ukraine received necessary spare parts for emergency diesel generators at the South Ukrainian NPP thanks to an agreement to support Ukrainian NPPs with France and NNEGC "Energoatom".
The IAEA noted that in the absence of external power supply, the nuclear plants will use equipment that ensures safe and reliable operation.
Source: Interfax-Ukraine
Read also
- We are tired: Trump made a sharp statement about the war in Ukraine
- The USA has provided Ukraine with Trump's plan to end the war: WSJ reveals details
- From supplying weapons to investing in production: the EU changes its strategy to support Ukraine
- British fighters intercepted Russian planes near NATO borders twice in a week
- The Kremlin Prepares the Russian Society for a Possible Prolonged Conflict with NATO - ISW
- The Land Law: Who is Now Protected from the Return of Property to the State